The thirty-eight templates
| Template | Who fills it in | Rows | When |
|---|---|---|---|
| Request for quotation (RFQ) | Buyer issues it; supplier fills in the response columns | One per line on the material requisition | When the RFQ goes out, and again when the offers come back. |
| Bid tabulation | Buyer (procurement or package engineer) | One per RFQ line, scope item or commercial term, side by side for three bidders | When the offers are in, next to the TBE. See the bid tabulation guide. |
| Technical deviation list | Manufacturer | Only the clauses where the offer differs | With every technical offer. See the deviation list guide. |
| Compliance matrix | Manufacturer | Every requirement in the specification | When the tender asks for a full clause-by-clause statement. See the compliance matrix guide. |
| URS response matrix | Equipment supplier (proposal or validation engineer) | One per requirement in the customer's user requirement specification (URS) | With an offer for pharmaceutical or bioprocess equipment, and again at design qualification. |
| Steam sterilizer tender compliance matrix | Sterilizer manufacturer or distributor (tender engineer) | One per requirement in the hospital's technical specification | With a bid for a hospital sterilizer tender. See EN 285 in a steam sterilizer tender. |
| Hygienic design requirement checklist | Food or beverage equipment supplier (proposal or design engineer) | One per requirement area in the customer's hygienic design specification | With an offer for food, dairy or beverage equipment. |
| HVAC submittal checklist | HVAC equipment manufacturer or representative (application engineer) | One per item the specification asks for in a technical submittal | Before each equipment submittal goes to the contractor. |
| TBE matrix | EPC or owner evaluator | Every evaluation criterion, side by side for three bidders | During technical bid evaluation. Manufacturers use it to check how an offer will be scored. |
| Clarifications and deviations cover sheet | Manufacturer | One page, plus the items that need an answer | On top of the deviation list, in both priced and unpriced copies. |
| Order acknowledgement and contract review checklist | Manufacturer (order engineer, sales or contracts manager) | One per point compared between the quotation and the purchase order | When the purchase order arrives, before you acknowledge it. See purchase order vs quotation review. |
| Vendor document register | Manufacturer (document controller or project manager) | One per document on the customer's vendor data requirements list (VDRL) | After award, until the final data book. See the manufacturing record book guide. |
| Submittal log | Equipment supplier on a construction project (project engineer or document controller) | One per submittal and revision | From award until the last closeout submittal is approved. |
| Class certificate checklist | Marine equipment supplier (project engineer or quality manager) | One per equipment item in the scope of supply | From order review until every item has its class documents, before delivery to the yard. |
| Requirements traceability matrix (RTM) | Manufacturer (project or quality engineer) | One per requirement, linked to design, verification and evidence | After award, when the contract asks you to prove each requirement was met. |
| Instrument index | Package builder (instrument engineer) | One per instrument tag on the P&IDs | From the first P&ID until the calibration certificates are filed. |
| Inspection and test plan (ITP) | Manufacturer (quality engineer) | One per inspection or test, in the order the work happens | Before manufacture starts, for the customer's approval. See the ITP guide. |
| Pressure vessel ITP | Vessel manufacturer (quality engineer) | One per inspection or test on a welded vessel, from material receipt to the final dossier | Before manufacture starts, for approval by the customer and the inspector. |
| Structural steel ITP | Steel fabricator (quality engineer) | One per inspection during fabrication, from material receipt to the fabrication dossier | Before steel is cut, for the customer's approval. |
| Wind tower section ITP | Wind tower fabricator (quality engineer) | One per operation on a tower section, from plate and flange receipt to the section dossier | Before the first plate is cut, for the turbine OEM's approval. |
| MTR review checklist | Quality or materials engineer | One per check on a material test report | At goods-in, before material is released to manufacture. |
| Sour service material checklist | Package builder or fabricator (quality or materials engineer) | One per pressure-containing or wetted part | At goods-in on a sour service order, and before the record book closes. See NACE MR0175/ISO 15156. |
| WPS/PQR/WPQ cross-check matrix | Welding coordinator or quality engineer | One per weld on the weld map | Before welding starts, and again before the record book is closed. |
| Welder continuity log | Welding coordinator | One per welder and process | Kept up to date through the year, and checked before each job. |
| Weld map index and weld log | Fabricator (welding coordinator and quality engineer) | One per weld on the weld map, plus one per repair | From the first weld until the record book is issued. See how to check WPS, PQR and WPQ against a weld map. |
| Rail welding documentation checklist | Rail component supplier (welding coordinator) | One per welding document held for a welded assembly | While the assembly is welded, and before the welding coordinator signs its release. |
| Pre-inspection checklist | Manufacturer (quality engineer) | One per condition that must be met before a hold or witness point | Before each inspection notification goes out. |
| Calibration certificate checklist | Manufacturer (test or quality engineer) | One per instrument named on a test report | Before a witnessed test, and when the test report is filed. See calibration certificates for test reports. |
| FAT readiness checklist | Manufacturer (test or quality engineer) | One per condition that must be met before the inspector arrives | Before the inspection notification goes out. See the FAT checklist guide. |
| Machine FAT protocol | Machine builder (project manager or commissioning engineer), signed with the customer | One per test, plus one per punch item | Agreed before the factory acceptance test, filled in and signed during it. |
| Routine test report checklist | Transformer or switchgear manufacturer (test or quality engineer) | One per check on a routine test report | After the tests, before the report goes to the customer. |
| Pump performance test record | Pump manufacturer (test-bed engineer) | One per test point, plus one per instrument used | On the day of the performance test, with the header filled in beforehand. |
| Valve test certificate checklist | Valve manufacturer (quality engineer) | One per check on a pressure test certificate | After the pressure tests, before the valve ships. |
| First article inspection report checklist | Aerospace component maker (quality engineer) | One per check on a first article inspection report | After the report is prepared, before it goes to the customer. |
| Load test certificate checklist | Crane or lifting equipment maker (commissioning or quality engineer) | One per point on a load test certificate | After the load test, before the equipment is handed over. |
| MRB index | Manufacturer (document controller) | One per section of the final record book | From kickoff until the record book is issued. See the manufacturing record book guide. |
| Nuclear quality record index | Nuclear equipment supplier (records controller) | One per quality record type for a safety-related item | From order review until the certificate of conformance is signed, and for as long as the records are kept. |
| Certificate of conformance (CoC) | Manufacturer (quality manager signs) | One per purchase order line shipped under the certificate | With each shipment, after final inspection is released. |
Each template page shows the example rows, explains every column and gives the steps to fill it in.
Download the templates
XLSX
Request for quotation (RFQ)
Line items with tags, datasheet and spec references, documents, inspection and delivery, plus supplier columns for compliance, deviation reference and lead time.
CSV
Request for quotation (RFQ)
The same columns as plain CSV.
XLSX
Bid tabulation (three bidders)
Buyer-side comparison: requirement line, then offered, compliance and price per bidder, a levelling note, row status and totals as quoted and as levelled.
CSV
Bid tabulation (three bidders)
The same columns as plain CSV.
XLSX
Technical deviation list
Spec clause, verbatim requirement, offered, status, alternative, justification, impact, cost of withdrawal and customer response.
CSV
Technical deviation list
The same columns as plain CSV, for Google Sheets or any tool.
XLSX
Clause-by-clause compliance matrix
One row per requirement, with type, offered value, status, evidence and deviation list item.
CSV
Clause-by-clause compliance matrix
The same columns as plain CSV.
XLSX
URS response matrix
URS ID, verbatim requirement, category, must or want, supplier response, status, reference document and the stage where it will be verified.
CSV
URS response matrix
The same columns as plain CSV.
XLSX
Steam sterilizer tender compliance matrix
Tender clause, verbatim requirement, standard called up, offered value, status, supporting document and remark.
CSV
Steam sterilizer tender compliance matrix
The same columns as plain CSV.
XLSX
TBE matrix (three bidders)
Evaluator-side matrix: criterion, mandatory flag, weight, and response, compliance, score and comments per bidder, with a calculated summary.
CSV
TBE matrix (three bidders)
The same columns as plain CSV.
XLSX
Clarifications and deviations cover sheet
Documents reviewed, calculated counts and the items that need the customer's answer.
CSV
Clarifications and deviations cover sheet
The items table as plain CSV.
DOCX
Clarifications and deviations cover letter
The same content as a one-page letter, for buyers who want a letter.
Markdown
Clarifications and deviations cover letter
The same letter as plain text.
XLSX
Order acknowledgement and contract review checklist
Purchase order against quotation: scope, revisions, agreed deviations, documents, inspection, delivery, price and terms, with a result and an action per row.
CSV
Order acknowledgement and contract review checklist
The same columns as plain CSV.
XLSX
Vendor document register
Post-award register: VDRL code, document, purpose, due date, revision, transmittal, review code, status, next action and data book section.
CSV
Vendor document register
The same columns as plain CSV.
XLSX
Requirements traceability matrix (RTM)
Requirement ID, source clause, agreed deviation, design reference, verification method and reference, evidence and status.
CSV
Requirements traceability matrix (RTM)
The same columns as plain CSV.
XLSX
Instrument index
Tag, service, type, P&ID, loop, location, range, signal, datasheet, calibration certificate, any specified SIL requirement, vendor and status.
CSV
Instrument index
The same columns as plain CSV.
XLSX
Inspection and test plan (ITP)
Step, activity, procedure, acceptance criteria source, record, and hold, witness and review points for manufacturer, customer and third party.
CSV
Inspection and test plan (ITP)
The same columns as plain CSV.
XLSX
Pressure vessel ITP
Vessel steps from material receipt to the final dossier, with reference document, acceptance criteria reference, record, and hold, witness, review and monitor points.
CSV
Pressure vessel ITP
The same columns as plain CSV.
XLSX
Structural steel ITP
Fabrication steps from material receipt to documentation, with governing document, acceptance criteria reference, extent, record, and hold, witness, review and monitor points.
CSV
Structural steel ITP
The same columns as plain CSV.
XLSX
MTR review checklist
Header block, 6 columns, result drop-down, a worked example and a How to use sheet.
CSV
MTR review checklist
The same columns as plain CSV.
XLSX
WPS/PQR/WPQ cross-check matrix
Header block, 16 columns, Y/N/Check drop-downs, a worked example and a How to use sheet.
CSV
WPS/PQR/WPQ cross-check matrix
The same columns as plain CSV.
XLSX
Welder continuity log
One row per welder and process, with last use, confirmation and next confirmation date.
CSV
Welder continuity log
The same columns as plain CSV.
XLSX
Weld map index and weld log
Weld number, drawing and sheet, joint, size, material, WPS, welder, weld date, visual and NDE results, repair cycle, PWHT record and release.
CSV
Weld map index and weld log
The same columns as plain CSV.
XLSX
Pre-inspection checklist
Every condition to meet before a hold or witness point: drawings, procedures, material certificates, welding and NDE records, calibration, NCRs and the notification.
CSV
Pre-inspection checklist
The same columns as plain CSV.
XLSX
Calibration certificate checklist
One row per instrument behind a test report: ID match, laboratory, accreditation, traceability, range, validity on the test date and as-found and as-left results.
CSV
Calibration certificate checklist
The same columns as plain CSV.
XLSX
FAT readiness checklist
Every condition to meet before the inspector arrives: procedure, earlier ITP steps, calibration, material, NCRs, documents and logistics.
CSV
FAT readiness checklist
The same columns as plain CSV.
XLSX
Routine test report checklist
Fifteen checks on a transformer or switchgear routine test report: test scope, results against specified values, instruments, witness, deviations and approval.
CSV
Routine test report checklist
The same columns as plain CSV.
XLSX
Pump performance test record
Rated-point header, test points with guaranteed and measured values side by side, instruments with calibration details, and a witness block.
CSV
Pump performance test record
The test point table as plain CSV.
XLSX
Valve test certificate checklist
Fifteen checks on a valve pressure test certificate: tests required against tests performed, medium, pressure, duration, gauges, witness and deviations.
CSV
Valve test certificate checklist
The same columns as plain CSV.
XLSX
Submittal log
One row per submittal and revision: specification section, type, dates submitted, required back and returned, review action, reviewer comments and resubmittal date.
CSV
Submittal log
The same columns as plain CSV.
XLSX
Machine FAT protocol
Test table with requirement reference, acceptance criterion as the contract writes it and result, plus a punch list sheet and a sign-off block.
CSV
Machine FAT protocol
The test table as plain CSV.
XLSX
Hygienic design requirement checklist
Twelve requirement areas from product-contact materials to documentation, each with the customer's clause, what is offered, a status and the evidence document.
CSV
Hygienic design requirement checklist
The same columns as plain CSV.
XLSX
Sour service material checklist
One row per pressure-containing or wetted part: material, the order's sour service clause, hardness and heat treatment wording, certificate type and what the certificate shows.
CSV
Sour service material checklist
The same columns as plain CSV.
XLSX
HVAC submittal checklist
Twelve items an equipment specification commonly asks for, each marked required and included, with the document reference and any deviation.
CSV
HVAC submittal checklist
The same columns as plain CSV.
XLSX
First article inspection report checklist
Fifteen checks on a first article inspection report, from part and drawing revision to certificates and sign-off, each with what the order requires and what the report shows.
CSV
First article inspection report checklist
The same columns as plain CSV.
XLSX
Rail welding documentation checklist
Fourteen welding documents for one welded assembly, each with what the drawing and order require, what is on file and a status.
CSV
Rail welding documentation checklist
The same columns as plain CSV.
XLSX
Nuclear quality record index
One row per quality record type: document number, the purchaser's clause, retention class as the purchaser specifies, approver, purchaser review status and location.
CSV
Nuclear quality record index
The same columns as plain CSV.
XLSX
Class certificate checklist
One row per marine equipment item: approval route, type approval certificate and expiry, drawings submitted, surveys, product and material certificates and the wheel mark.
CSV
Class certificate checklist
The same columns as plain CSV.
XLSX
Load test certificate checklist
Fifteen points on a crane or lifting equipment load test certificate, each with what the contract specifies and what the certificate records.
CSV
Load test certificate checklist
The same columns as plain CSV.
XLSX
Wind tower section ITP
Eighteen operations on one tower section with reference document, acceptance criteria reference, record and intervention codes for fabricator, OEM and third party.
CSV
Wind tower section ITP
The same columns as plain CSV.
XLSX
MRB index
Record book sections with the VDRL or clause that asks for each, document numbers, revisions, tags and heats covered, and status.
CSV
MRB index
The same columns as plain CSV.
XLSX
Certificate of conformance (CoC)
Certificate form: header block, table of items certified with drawing revisions and serial numbers, example statement and signature block.
CSV
Certificate of conformance (CoC)
The item table as plain CSV.
To open a CSV in Google Sheets, choose File, then Import, then Upload. The XLSX files open in Excel, Google Sheets, LibreOffice and Numbers.
What is in each spreadsheet
- A blank working sheet with a header block for project, customer, RFQ or purchase order number, revision and who prepared and checked it.
- A filled-in example sheet for an invented 6-inch Class 600 trunnion ball valve specification (PS-VAL-001), the invented order placed against it (PO-EX-3105), an invented vessel order (PO-EX-4410), an invented URS (URS-EX-5120) or an invented hospital tender (T-EX-7702). Delete it before you send the file.
- A How to use sheet with the steps, the status values and what to write in each column.
- Drop-downs for status and other fixed values, colour-coded Deviation and Clarification rows, a frozen header row, filters and print settings.
The CSV files carry the example rows only. Every example value is invented; standards such as API 6D and ISO 15848-1 are named but not quoted.
Use the templates with OdysseyGPT
The templates work on their own. If you would rather start from a draft, OdysseyGPT checks each customer requirement against your own datasheets, gives it a status with a quote from the source page, sheet or cell, and exports an editable compliance matrix and deviations & clarifications list. A bid engineer, proposal engineer or project manager then decides every open item and adds the justification and cost of withdrawal. See OdysseyGPT for manufacturing, or try the free spec requirement extractor on a few pages of specification text.